Phase 2 Progress
91% (8% Ahead)
R10.6M

Contract Value (incl. VAT)

Transit
infrastructure
revitalized.

PRASA: Refurbishment and Renovation of Chris Hani Station in Khayelitsha, Cape Town.

PRASA

Chris Hani
Station.

Contract WCR/CRES/02/08/2024

Anti-Bandit Doors Bulletproof Glazing Ablutions & Mirrors Fencing 95% 12 MONTHS DURATION
PROJECT LOG

Key Milestones.

Report: 02 Dec 2025
Compiled by G. Victor Ngoveni

BEFORE AFTER
Station progress
Progress photos – ablution facilities

Programme Status

Phase 1 (Basic Functionality)

100% Complete

Phase 2 (Overall Works)

91% (8% Ahead)

Planned Completion

12 Dec 2025

"Currently attending to visible snags to ensure quality handover."

PROJECT NARRATIVE

Chris Hani Station: A Critical Upgrade for PRASA

Revitalizing public transport infrastructure in the Western Cape.

The comprehensive refurbishment and renovation of Chris Hani Station, executed by the DINGA SOMBS JV on behalf of PRASA, is a landmark project restoring dignity and safety to a key commuter hub in Khayelitsha, Cape Town. With a contract value of R10,625,756.97 (incl. VAT), the project spans new ablutions, security hardening, electrical works, and civil infrastructure.

Scope of Work

  • Ablutions & Public Facilities: Installation of public toilets, mass area mirrors, handwash basins, accessible grab rails, and toilet roll holders.
  • Security Hardening: Anti-bandit doors, bulletproof glazing for the ticket office, PA system setup, and perimeter fencing (95% complete).
  • Electrical & Lighting: Platform shelter lights, kiosks, flood lighting, and walkway lights.
  • Civil Works: Driveway layer works, asphalt resurfacing, and stormwater management preparation.

Current Execution & Technical Installations

Phase 2 is tracking 8% ahead of schedule, with 91% of work completed against an 83% time elapse. Key installations in progress include:

  • Ticket Office Security: Anti-bandit doors and bulletproof glazing are in manufacturing, expected by mid‑December 2025. Existing door frames will be removed prior to delivery.
  • Electronics & PA: Engagement with Vhukudo Security Systems underway; however, additional guidance is required for the broader electronics scope.
  • Perimeter Fencing: 95% complete. The remaining 5% is delayed by a neighbouring scrapyard encroaching onto PRASA property.
  • HVAC: Awaiting final fan installation before commissioning and full testing.

Challenges & Resolutions

Challenge Status / Notes
Electronics Budget Struggling to execute scope within budget.
Material Availability Specialised PA components facing availability issues.
Delivery Timelines Builders break affecting production items; providers pushing for December delivery.
Financial / Payment Delays Overdue payments to Tri-Fink Roofing and Topfence.
Labor Issues Site labourers not yet paid.

Project Timeline

Start Date

30 Jan 2025

Target Completion

30 Jan 2026

Duration

12 Months

Planned Completion

12 Dec 2025

Client: PRASA | Contractor: DINGA SOMBS JV | Site Manager: G. Victor Ngoveni