The comprehensive refurbishment and renovation of Chris Hani Station, executed by the DINGA SOMBS JV on behalf of PRASA, is a landmark project restoring dignity and safety to a key commuter hub in Khayelitsha, Cape Town. With a contract value of R10,625,756.97 (incl. VAT), the project spans new ablutions, security hardening, electrical works, and civil infrastructure.
Scope of Work
- Ablutions & Public Facilities: Installation of public toilets, mass area mirrors, handwash basins, accessible grab rails, and toilet roll holders.
- Security Hardening: Anti-bandit doors, bulletproof glazing for the ticket office, PA system setup, and perimeter fencing (95% complete).
- Electrical & Lighting: Platform shelter lights, kiosks, flood lighting, and walkway lights.
- Civil Works: Driveway layer works, asphalt resurfacing, and stormwater management preparation.
Current Execution & Technical Installations
Phase 2 is tracking 8% ahead of schedule, with 91% of work completed against an 83% time elapse. Key installations in progress include:
- Ticket Office Security: Anti-bandit doors and bulletproof glazing are in manufacturing, expected by mid‑December 2025. Existing door frames will be removed prior to delivery.
- Electronics & PA: Engagement with Vhukudo Security Systems underway; however, additional guidance is required for the broader electronics scope.
- Perimeter Fencing: 95% complete. The remaining 5% is delayed by a neighbouring scrapyard encroaching onto PRASA property.
- HVAC: Awaiting final fan installation before commissioning and full testing.
Challenges & Resolutions
| Challenge | Status / Notes |
|---|---|
| Electronics Budget | Struggling to execute scope within budget. |
| Material Availability | Specialised PA components facing availability issues. |
| Delivery Timelines | Builders break affecting production items; providers pushing for December delivery. |
| Financial / Payment Delays | Overdue payments to Tri-Fink Roofing and Topfence. |
| Labor Issues | Site labourers not yet paid. |
Project Timeline
Start Date
30 Jan 2025
Target Completion
30 Jan 2026
Duration
12 Months
Planned Completion
12 Dec 2025
Client: PRASA | Contractor: DINGA SOMBS JV | Site Manager: G. Victor Ngoveni